World Series Week of November 17, 2014 | KC Downtown Streetcar Construction Update

Crossroads Central Business District River Market

Highlights

Cold Weather and Snow 
As the winter and potential for snow approaches, KC Streetcar Constructors (KCSC) is committed to maintaining safe conditions along the future streetcar route for the traveling public and its crews. Please read about the full cold weather and snow plan on the KC Streetcar website

5th and Grand Track Work
Fifth Street will close starting Monday, November 17 for 10 days from Grand Boulevard to just east of Walnut while the KC Streetcar Constructors builds the curved track in the intersection of 5th Street and Grand Boulevard. Read more about the track work on the KC Streetcar website

Central Business District 
Crews are working 24/7 for approximately 4-5 weeks performing water work near Truman Road North and travel north mid-block between 12th and 13th Streets. 

This Week

CROSSROADS
Pershing to 20th
East side of bridge: Track slab concrete is curing through November 15.
20th to 17th
Side-street lane restrictions due to water work
  • 20th, one lane of eastbound and westbound traffic between Main and Walnut
Anticipated completion of all water work in this segment by mid-November.
West side track work wrapping up from 17th to mid-18th St. 

20th to 17th: Power pole foundation work. This will mainly affect sidewalks and curb running lanes.
View an overview map of current street closures online
17th to Truman Road south
Truman Road South at Main St water work to anticipated completion November 15.
Track work ongoing on east side of Main St from Truman Rd South to just south of 17th St. 

Side-street closures due to track and water work:
  • 16th St closed Baltimore to Walnut
  • Truman Road south, Baltimore to Main (weekdays only)
View a map of the Truman Rd South closure online
CENTRAL BUSINESS DISTRICT
Truman Road north to 12th
Truman Road north through 13th: Various lane closures due to water work. Crews working 24/7. Anticipated completion in mid-November.

Tentative: 11/17-11/19: 13th St closed Walnut to Main.
12th to 10th
Main, 11th to 12th: Various lane drops will occur while KCP&L, Time Warner Cable, and AT&T complete work in this segment. Work is anticipated to continue through October.

10th & Main: Private utility work is now on the southeast corner. 10th, Baltimore to Main, remains one-way eastbound until the private utility work at all four corners of the intersection has been completed. Anticipated completion: December 2014.

Petticoat open to local traffic only. No parking along Petticoat.

View an overview map of related street restrictions online
10th to 7th
10th & Main: Private utility work is now on the southeast corner. 10th, Baltimore to Main, remains one-way eastbound until the private utility work at all four corners of the intersection has been completed. Anticipated completion: December 2014.

10th & Main is an active work zone. Suggested pedestrian crossing at either 9th St or Petticoat Lane. 

7th & Main: Sewer work. Anticipated completion: mid-November.

Power pole foundation work throughout this segment. Brief impacts to sidewalks and curb-running lanes during this work.
7th to Independence
Delaware Bridge (over I-70): Open to one lane of traffic each direction. 
RIVER MARKET
5th, Delaware to Grand
Track Work:
11/17: 5th Street closed until November 26 from Grand Boulevard to just east of Walnut while KC Streetcar Constructors builds the curved track in the intersection of 5th Street and Grand Boulevard.  


11/15-11/18: Grand Blvd.from 3rd St to 5th St open to southbound traffic only.

11/19: Grand Blvd, from 5th Street to 3rd Street, will be local access only from 3rd Street. Businesses and parking lots on Grand Boulevard will remain accessible from 3rd Street. 

11/17: 5th Street from Walnut to Delaware reopened to two-way traffic.


Water work: 
10/6-11/21: Water work on Walnut St from 5th St. to Missouri. Water shut scheduled for 11/21 12:01am-8:00am. 


Visit kcstreetcar.org for a map and detour information.
Grand, 5th to 3rd
11/15-11/18: Grand Blvd.from 3rd St to 5th St open to southbound traffic only.

11/19: Grand Blvd, from 5th Street to 3rd Street, will be local access only from 3rd Street. Businesses and parking lots on Grand Boulevard will remain accessible from 3rd Street. 
3rd, Delaware to Grand
Minimal construction activity.
Delaware, Independence to 3rd
Water work ongoing on Delaware between 3rd and Independence Ave. One lane of southbound traffic only. No on-street parking on Delaware between 3rd and Independence Ave. Parking diverted to Wyandotte St. and 3rd St. Anticipate completion week of 11/17. 

Water work on 4th, Delaware and heading east. Anticipate end of week of 11/17.

Water work on Delaware between 5th and Independence. One lane of traffic southbound only. No on-street parking on Delaware. 

OCS work on westside of Delaware between 3rd-5th Street. Anticipate completion 11/21.
Grand to Vehicle Maintenance Facility
Foundation piers are being drilled and concrete is being poured.  Exterior wall construction for the "Singleton Yard" vehicle maintenance facility. Pre-cast concrete wall panels to be delivered to the site in mid-December.
 

 



Private utility work will continue through fall 2014. KC Streetcar Constructors will continue track work in the River Market in fall 2014 as well as through the Crossroads area.  
About the Downtown Kansas City Streetcar Starter Line
The two-mile, north-south Downtown KC Streetcar will travel along Main Street and connect the River Market to Crown Center and Union Station, serving the Central Business District, the Crossroads Art District, and the Power and Light District, as well as numerous businesses, restaurants, art galleries, educational facilities and residents. 

For more information visit us on the Web, Facebook and Twitter or contact the Project Hotline at 816.804.8882 or info@kcstreetcar.org.
About KC Streetcar Constructors 
KC Streetcar Constructors (KCSC) is the project team building the two-mile KC Downtown Streetcar starter line. KCSC is a joint venture of St. Joseph-based Herzog Contracting Corp. and California rail builder Stacy and Witbeck, Inc.

About this Update
This weekly construction update provides weekly, at-a-glance information related to the streetcar construction that is taking place this week.  For more information, including upcoming work, check out the project website and follow the streetcar on Twitter (@kcstreetcar) and Facebook. All work activities and time frames are subject to change due to inclement weather or other unforeseen circumstances. 

This update is organized into 12 construction segments, starting at the southern end of the project at Union Station and working north through the River Market. 