Week of March 2, 2015 | KC Downtown Streetcar Construction Update
Nearing the halfway point.
Construction of the downtown KC Streetcar has made steady progress regardless of the cold temperatures and recent snow. Track construction is at 47% and water/sewer work at 88%.
New format! This format focuses on the activities that have the greatest impact to the traveling public this week. If there is work scheduled for the week that involves significant traffic impacts, such as lane closures, detours, or parking restrictions, you will find it below with the key details and type of work noted in parenthesis.
For more detailed information, including projected work duration or a "look ahead", please visit the KC Streetcar website. For the most up-to-date info follow the project on twitter @kcstreetcar.
|
|
- Various lane closures and lane shifts Truman Rd south to 20th. (systems and track)
|
|
|
|
|
|