Week of February 23, 2015 | KC Downtown Streetcar Construction Update

New format! We streamlined the information in an effort to focus on the activities that have the greatest impact to the traveling public. If there is work scheduled for the week that involves significant traffic impacts, such as lane closures, detours, or parking restrictions, you will find it below with the key details and type of work noted in parenthesis.  

For more detailed information, including projected work duration or a "look ahead", please visit the KC Streetcar website. For the most up-to-date info follow the project on twitter @kcstreetcar
CROSSROADS
  • Various lane closures and lane shifts Truman Rd south to 20th. (systems and track) 
CENTRAL BUSINESS DISTRICT
  • Lane closures Truman Road north through 13th. (systems and private utility) 
  • Lane closures at 12th and Main. (water)
  • NIGHT WORK & Closure on Main between 9th and 10th, 7pm-5am, Mondays-Fridays. Main closed between 9th-10th at night with no on-street parking. 9th closed east and west of Main St, 24/7, with local access for deliveries and garages only. Loud construction work to occur prior to 10:30pm. All work is weather permitting. (water)  Map of closure
RIVER MARKET
  • Delaware, 3rd to Independence, closed.  Parking available on 3rd, 5th, and in area public parking lots. DE Loft Parking Lot at the southeast corner of 5th and Delaware accessible from Independence instead of 5th. Anticipated reopen the week of March 9 (track)
  • 5th eastbound only from Delaware to just west of Main. The eastern entrance to the City Market parking lot will be accessible from the west and the east. 5th will remain this way until around the second week of March. (track)
  • No on-street parking on 3rd, from Grand to Main. (water)
  • Delaware, 2nd-3rd Streets, southbound traffic only. No on-street parking. (water)

 

Anticipated completion of all private (third-party) utility work is Spring 2015. KC Streetcar Constructors' track work continues in the River Market, Crossroads and Power and Light District into April 2015.  Water/sewer work anticipated to be complete by late Spring 2015. Systems work, such as the overhead power system, will continue through Summer 2015.
About the Downtown Kansas City Streetcar Starter Line
The two-mile, north-south Downtown KC Streetcar will travel along Main Street and connect the River Market to Crown Center and Union Station, serving the Central Business District, the Crossroads Art District, and the Power and Light District, as well as numerous businesses, restaurants, art galleries, educational facilities and residents. 

For more information visit us on the Web, Facebook and Twitter or contact the Project Hotline at 816-804-8882 or info@kcstreetcar.org.
About KC Streetcar Constructors 
KC Streetcar Constructors (KCSC) is the project team building the two-mile KC Downtown Streetcar starter line. KCSC is a joint venture of St. Joseph-based Herzog Contracting Corp. and California rail builder Stacy and Witbeck, Inc.
About this Update
This weekly construction update provides weekly, at-a-glance information related to the streetcar construction that is taking place this week.  For more information, including upcoming work, check out the project website and follow the streetcar on Twitter @kcstreetcar and Facebook. All work activities and time frames are subject to change due to inclement weather or other unforeseen circumstances. 
Copyright © 2015 KC Streetcar Authority, All rights reserved.

unsubscribe from this list    update subscription preferences