Week of May 11, 2015 | KC Downtown Streetcar Construction Update
KC Streetcar Construction on Budget and Schedule
Streetcar construction remains on schedule and on budget, with all key construction activities at least 70 percent complete. Streetcar construction is on schedule to be completed in fall of 2015. The streetcar system will then undergo a period of testing and is anticipated to be open to the public in 2016.
Currently, traffic is extremely congested in the Central Business District between 8th - 12th Streets as crews build track and work on station electrical and cable systems on the west side of Main Street. Please check the construction map on www.kcstreetcar.org and our twitter feed (@kcstreetcar) daily for road closures updates.
For more detailed information about streetcar construction, including projected work duration or a "look ahead", please visit the KC Streetcar website. For the most up-to-date info follow the project on twitter @kcstreetcar.
|
|
- Permanent street signage installation from Truman Rd South - 20th St. (two weeks)
- Truman Rd South North lane closed between Baltimore-Main. (power station)
- Lane shifts on east side of Main between Truman Rd South and 16th St. (station platform)
- 5/11 - 5/15: Right lane closed at 19th & Main. Work at corners of 19th & Main (systems).
- 5/13 - 5/20: Corner restoration work at 16th & Main and 17th & Main.
- Traffic is now on the east side on the Main St Viaduct, south of 20th St. (track). Dedicated lane for Bus loading and unloading only on the east side. Work includes track turnout construction and installation of OCS poles 5/13 - 5/15.
- NON-STREETCAR WORK taking place on 20th St between McGee and SW Blvd. Work being performed by Kansas City's Water Services Department and anticipated to take two months.
- NON-STREETCAR WORK taking place at 19th & Grand. Work will impact sidewalks and curb lanes. Work being performed by Kansas City's Public Works Department with Mark One Electric. Work anticipated to take 2-3 weeks.
|
|
|
|
|
|