Week of June 8, 2015 | KC Downtown Streetcar Construction Update
3rd & Grand Track Work
Work on one of the last pieces of track will start the week of June 15, 2015. This is the special turn piece that will connect Grand to 3rd St. During work, 3rd will be closed from Walnut-Grand and Grand will be open to southbound only from 3rd to Missouri Ave. This will be in place for 3 weeks, including weekends. Click on the above image for a full map.
Currently, traffic is extremely congested in the Central Business District between 8th - 12th Streets as crews work on northbound track on the east side of Main Street. Please check the construction map on www.kcstreetcar.org and our twitter feed (@kcstreetcar) daily for road closures updates.
For more detailed information about streetcar construction, including projected work duration or a "look ahead", please visit the KC Streetcar website. For the most up-to-date info follow the project on twitter @kcstreetcar.
|
|
- Lane shifts on east side of Main between Truman Rd South & 16th St for station platform work & power sub station work.
- Restoration work at southeast corner of 16th & Main.
- Traffic signal replacements at the corners of 19th & Main. Look for lane shifts.
- 5/26 - 7/3: Station stop platform work on northeast corner of 19th & Main. East lane closed. Traffic shifted to the west.
- Track turnout construction & pour on Main St Viaduct. Traffic pushed to east side of Main, south of 20th St. Dedicated lane for Bus loading and unloading only on the east side.
- OCS pole catenary arm installation from Truman Rd South - 20th St. Traffic pushed to the center lanes.
- NON-STREETCAR WORK taking place on 20th St between McGee and SW Blvd. Work being performed by Kansas City's Water Services Department and anticipated to take two months.
- NON-STREETCAR WORK traffic signal work taking place at 19th & Grand. Work will impact sidewalks and curb lanes. Work being performed by Kansas City's Public Works Department with Mark One Electric.
|
|
|
|
|
|